TNPRC RBL - Week of January 26, 2024

Sources of Noise

  • Hand Tools.
  • Small man lift.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials.

Events for upcoming week

  • Begin soldering plumbing pipes in the Penthouse.
  • Electrical rough in in the Lab area and Penthouse ongoing.
  • Continue mechanical rough in for the Lab area and Penthouse.
  • Install Copy Room door and hardware.
  • Layout rooftop units.

Recap of week ending January 19, 2024

  • Coordinated hot work with Securance, TU Police, and Facilities.
  • Core drilled concrete floor in multiple locations for MEP routing.
  • Mechanical layout began.
  • Electrical rough in ongoing.