Sources of Noise
- Hand Tools.
- Small man lift.
- Core drill machine.
Utility Shutdowns
- None at this time.
Deliveries
- Materials.
Events for upcoming week
- Continue drywall finishes on the corridor side.
- Insulate and hang drywall on the interior lab wall.
- X-Ray and core drill concrete in multiple locations for MEP routing.
- Continue electrical rough in.
- Resume Penthouse plumbing rough in.
- Pull door access circuits, install hardware, and energize.
- Finalize Offices 1 through 4 punch list items.
- Clean offices for new occupants.
Recap of week ending January 5, 2024
- Routed door access and Data conduits to Offices 1 through 4.
- Patched in newly pulled Data circuits.
- Poured concrete pad for the electrical transformer in Penthouse.
- Demo’d MEP as needed.
- Started drywall finishes on the corridor side.
- Removed temp wall.