TNPRC RBL - Week of January 12, 2024

Sources of Noise

  • Hand Tools.
  • Small man lift.
  • Core drill machine.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials.

Events for upcoming week

  • Continue drywall finishes on the corridor side.
  • Insulate and hang drywall on the interior lab wall.
  • X-Ray and core drill concrete in multiple locations for MEP routing.
  • Continue electrical rough in.
  • Resume Penthouse plumbing rough in.
  • Pull door access circuits, install hardware, and energize.
  • Finalize Offices 1 through 4 punch list items.
  • Clean offices for new occupants.

Recap of week ending January 5, 2024

  • Routed door access and Data conduits to Offices 1 through 4.
  • Patched in newly pulled Data circuits.
  • Poured concrete pad for the electrical transformer in Penthouse.
  • Demo’d MEP as needed.
  • Started drywall finishes on the corridor side.
  • Removed temp wall.