TNPRC RBL - Week of February 9, 2024

Sources of Noise

  • Truck Crane.
  • Hand Tools.
  • Small man lift.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Truck Crane.

Events for upcoming week

  • Penetrate roof to accommodate new equipment.
  • Set roof curbs.
  • Patch roof curbs and dry in area.
  • Mechanical rough in.
  • Electrical rough in.

Recap of week ending February 2, 2024

  • Crane lifted and installed exterior stairs, landing, and assemblies.
  • Roofers patched around the stair and landing supports.
  • Siemens disabled door hardware to accommodate new Copy Room door.
  • New Copy Room door installed.
  • Began duct hangers.
  • Plumbing rough in ongoing.
  • Continued electrical rough in.