TNPRC Building 20 Lab Renovation - Week of December 22, 2023

Sources of Noise

  • Hand Tools.
  • Small man lift.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials.

Events for upcoming week

  • Continue and complete framing the new Lab wall.
  • Hang drywall, occupant side only.
  • Start drywall finishes.
  • MEP Demo ongoing.

Recap of week ending December 15, 2023

  • Installed temporary wall for Lab construction.
  • Removed ceiling and carpet tiles in Lab area.
  • Demo’d exiting light fixtures.
  • Pulled and discarded floor receptacles and data line floor hubs.
  • Began framing new Lab wall.
  • Explored newly discovered routing for door access and Data.
  • Finished upper East side of Offices 1 and 2. 
  • Removed temporary wall and floor protection East side of Offices 1 and 2.