Sources of Noise
- Vehicles
- Dumpsters
- Tools/ Equipment
Utility Shutdowns
- None at this time
Deliveries
- General construction materials and dumpsters.
Events for upcoming week
- Continue MEP install all floors. Insulate ducts and Tape/ float/ finish drywall as available.
- Continue exterior window sealing West façade.
- Continue Window restorations.
- Continue masonry clean up and NE exterior brick installation. Continue to erect scaffolding for East central exterior tuck-pointing.
- Continue vaulted ceiling installation of 5th floor central ceiling lid.
- Continue Low voltage systems installation.
- Continue Sprinkler installation. Inspect as areas become available.
- Remove excess scaffolding materials.
- Begin Elev 2.
- Set fire pump and electrical generator in place.
- Begin West exterior scaffold removal.
- Scan 2nd floor lobby stair capitals.
- Continue RTU piping and ducting.
Recap of Week ending March 18, 2024
- Continue Mechanical, ceiling, and plumbing inspections on prepared system segments by TBES team.
- Continue MEP installations throughout.
- Continue low voltage install. Continue terminating data jacks throughout.
- Continue window restorations.
- Continue Sprinkler system pipe installation. Prime and paint pipes
- Continue Site clean-up and mat relocations.
- Continue ceiling installations 2nd floor.
- Continue with 5th floor vaulted ceiling finishing/ painting. Remove high scaffold on 4th floor studios.
- Continue Elev 1 installation.
- Continue Northeast exterior brick laying. Address West brick punchlist.