RMH - Week of March 29, 2024

Sources of Noise

  • Vehicles
  • Dumpsters
  • Tools/ Equipment

Utility Shutdowns

  • None at this time

Deliveries 

  • General construction materials and dumpsters. 

Events for upcoming week

  • Continue MEP install all floors. Insulate ducts and Tape/ float/ finish drywall as available.
  • Continue exterior window sealing West façade. 
  • Continue Window restorations.
  • Continue masonry clean up and NE exterior brick installation. Continue to erect scaffolding for East central exterior tuck-pointing.
  • Continue vaulted ceiling installation of 5th floor central ceiling lid.
  • Continue Low voltage systems installation.
  • Continue Sprinkler installation. Inspect as areas become available.
  • Remove excess scaffolding materials.
  • Begin Elev 2.
  • Set fire pump and electrical generator in place.
  • Begin West exterior scaffold removal.
  • Scan 2nd floor lobby stair capitals. 
  • Continue RTU piping and ducting.

Recap of Week ending March 18, 2024

  • Continue Mechanical, ceiling, and plumbing inspections on prepared system segments by TBES team. 
  • Continue MEP installations throughout.
  • Continue low voltage install. Continue terminating data jacks throughout.
  • Continue window restorations. 
  • Continue Sprinkler system pipe installation. Prime and paint pipes 
  • Continue Site clean-up and mat relocations.
  • Continue ceiling installations 2nd floor.
  • Continue with 5th floor vaulted ceiling finishing/ painting. Remove high scaffold on 4th floor studios.
  • Continue Elev 1 installation.
  • Continue Northeast exterior brick laying. Address West brick punchlist.