Sources of Noise
- Vehicles
- Dumpsters
- Tools/ Equipment
Utility Shutdowns
- None at this time
Deliveries
- General construction materials
Events for upcoming week
- Continue exterior tuckpointing.
- Continue interior brick demo, infill, and lintel installations.
- Move to NW exterior for tuck pointing as weather permits.
- Continue MEP installation throughout.
- Continue closing walls on 2nd floor and building out Mechanical rooms on the 3rd and 4th floor. Layout the 5th floor.
- Continue South addition store front installation.
- Continue East waterproofing.
- Complete wood shop fire lid.
- Continue fire alarm installation.
- Continue Data, CCTV, Access, and AV installation.
- Continue SE excavation and debris removal for Dinwiddie permanent power.
- Continue Elevator guide rail installation.
- Inspect plumbing where available Wed, 24 Jan.
- TUSA tour Thursday, 25 Jan 24.
- Continue Sprinkler pipe installation.
Recap of January 8, 2024 – January 14, 2024
- Complete SE electrical pedestal removal.
- Continue interior Lintels, brick infills, and brick removal where required.
- Continue MEP Install.
- Continue interior wall framing and drywall installation, mainly on 2nd, 3rd, and 4th floors.
- Continue Wood shop fire lid installation.
- Begin removing grout debris from 1st floor exterior SW windows.
- Continue low voltage installation.
- Met with Data, Access control, and installation groups to layout the IT closets.
- Begin Elevator guide rail installation North elevator (ELEV 1).
- Begin Sprinkler system pipe installation.