RMH - Week of January 26, 2024

Sources of Noise

  • Vehicles
  • Dumpsters
  • Tools/ Equipment

Utility Shutdowns

  • None at this time

Deliveries 

  • General construction materials

Events for upcoming week

  • Continue exterior tuckpointing.
  • Continue interior brick demo, infill, and lintel installations.
  • Move to NW exterior for tuck pointing as weather permits.
  • Continue MEP installation throughout.
  • Continue closing walls on 2nd floor and building out Mechanical rooms on the 3rd and 4th floor. Layout the 5th floor.
  • Continue South addition store front installation.
  • Continue East waterproofing.
  • Complete wood shop fire lid. 
  • Continue fire alarm installation.
  • Continue Data, CCTV, Access, and AV installation.
  • Continue SE excavation and debris removal for Dinwiddie permanent power.
  • Continue Elevator guide rail installation.
  • Inspect plumbing where available Wed, 24 Jan.
  • TUSA tour Thursday, 25 Jan 24.
  • Continue Sprinkler pipe installation.

Recap of January 8, 2024 – January 14, 2024

  • Complete SE electrical pedestal removal.
  • Continue interior Lintels, brick infills, and brick removal where required.
  • Continue MEP Install.
  • Continue interior wall framing and drywall installation, mainly on 2nd, 3rd, and 4th floors. 
  • Continue Wood shop fire lid installation. 
  • Begin removing grout debris from 1st floor exterior SW windows.
  • Continue low voltage installation.
  • Met with Data, Access control, and installation groups to layout the IT closets. 
  • Begin Elevator guide rail installation North elevator (ELEV 1). 
  • Begin Sprinkler system pipe installation.