Sources of Noise
- Vehicles
- Dumpsters
- Tools/ Equipment
Utility Shutdowns
- Electrical shut down 8 a.m.-10 a.m. on Dec. 18, 2023
Deliveries
- General construction materials
Events for upcoming week
- Excavate for Dinwiddie power routing.
- Continue to close walls and finish ceilings 1st and 2nd floors.
- Continue framing walls on 3rd floor addition, 4th floor.
- Inspect 1st and 2nd floor plumbing, 3rd floor south walls, and duct work that is ready.
- Continue window restorations.
- Continue MEP installation throughout.
- Add scaffolding on the North façade to allow tuckpointing. Continue West tuck pointing.
- Continue interior masonry work. Mortar and brick infill along with penetrations as needed for bathrooms.
Recap of Dec. 18, 2023 – Jan. 7, 2024
- Electrical shut down successfully routed temp power to Dinwiddie Hall while permanent power is routed underground.
- Building cleaned up.
- Continued MEP installation.
- Continued exterior and interior masonry work. Tuck pointing, cutting penetrations, and infill as required.
- Receive 3rd floor ducts.
- Insulate interior of precast panels and apply intumescent paint on 4th floor truss and support steel.
- Continued exterior waterproofing on South addition.
- Continued low voltage conduit and wiring.
- Continued closing walls and finishing ceilings on 1st and 2nd floor.
- Continued windowsill fabrications and installations.
- Demo old Fire escape doorways on the Northeast and Southeast.