RMH - Week of January 12, 2024

Sources of Noise

  • Vehicles
  • Dumpsters
  • Tools/ Equipment

Utility Shutdowns

  • Electrical shut down 8 a.m.-10 a.m. on Dec. 18, 2023

Deliveries 

  • General construction materials

Events for upcoming week

  • Excavate for Dinwiddie power routing.
  • Continue to close walls and finish ceilings 1st and 2nd floors.
  • Continue framing walls on 3rd floor addition, 4th floor.
  • Inspect 1st and 2nd floor plumbing, 3rd floor south walls, and duct work that is ready.
  • Continue window restorations.
  • Continue MEP installation throughout.
  • Add scaffolding on the North façade to allow tuckpointing. Continue West tuck pointing.
  • Continue interior masonry work. Mortar and brick infill along with penetrations as needed for bathrooms.

Recap of Dec. 18, 2023 – Jan. 7, 2024

  • Electrical shut down successfully routed temp power to Dinwiddie Hall while permanent power is routed underground.
  • Building cleaned up.
  • Continued MEP installation.
  • Continued exterior and interior masonry work. Tuck pointing, cutting penetrations, and infill as required.
  • Receive 3rd floor ducts.
  • Insulate interior of precast panels and apply intumescent paint on 4th floor truss and support steel.
  • Continued exterior waterproofing on South addition.
  • Continued low voltage conduit and wiring.
  • Continued closing walls and finishing ceilings on 1st and 2nd floor.
  • Continued windowsill fabrications and installations.
  • Demo old Fire escape doorways on the Northeast and Southeast.