Sources of Noise
- Vehicles
- Dumpsters
- Tools/ Equipment
Utility Shutdowns
- None at this time
- West road for Crane lift for RTU supports.
Deliveries
- General construction materials and dumpsters.
Events for upcoming week
- Continue MEP installation all floors.
- Begin West Scaffold removal.
- Begin South HVAC riser walls on floors 2-5.
- Begin rooftop duct installation.
- Begin raised floor seating area. (rm 204).
- Continue duct shaft wall installation where available.
- Continue Low voltage installation.
- Continue TFF (Tape, Float, Finish)1st and 2nd floor.
- Continue 5th floor center vaulted ceiling install and 4th floor wall framing.
- Continue Sprinkler installation.
- Continue Elev 1 install.
Recap of Week ending March 31, 2024
- Continue MEP installation all floors.
- Punch list West faced.
- Continue window restorations.
- Continued East masonry.
- Set fire pump controller and poured pads for equipment.
- Dismantle/ begin removing 4th floor apex scaffolding.
- Continue Low Voltage installations.
- Scanned 2nd floor lobby capitals.
- Continue rooftop piping and electrical installation.
- Continue sprinkler installation.
- Continue Elev 1 installation.