RMH-Week of April 5, 2024

Sources of Noise

  • Vehicles
  • Dumpsters
  • Tools/ Equipment

Utility Shutdowns

  • None at this time
  • West road for Crane lift for RTU supports.

Deliveries 

  • General construction materials and dumpsters. 

Events for upcoming week

  • Continue MEP installation all floors.
  • Begin West Scaffold removal.
  • Begin South HVAC riser walls on floors 2-5.
  • Begin rooftop duct installation.
  • Begin raised floor seating area. (rm 204).
  • Continue duct shaft wall installation where available.
  • Continue Low voltage installation.
  • Continue TFF (Tape, Float, Finish)1st and 2nd floor.
  • Continue 5th floor center vaulted ceiling install and 4th floor wall framing.
  • Continue Sprinkler installation.
  • Continue Elev 1 install.

Recap of Week ending March 31, 2024

  • Continue MEP installation all floors.
  • Punch list West faced.
  • Continue window restorations.
  • Continued East masonry.
  • Set fire pump controller and poured pads for equipment.
  • Dismantle/ begin removing 4th floor apex scaffolding.
  • Continue Low Voltage installations.
  • Scanned 2nd floor lobby capitals.
  • Continue rooftop piping and electrical installation.
  • Continue sprinkler installation.
  • Continue Elev 1 installation.