Richardson Memorial - Week of March 1, 2024

Sources of Noise

  • Vehicles
  • Dumpsters
  • Tools/ Equipment

Utility Shutdowns

  • None at this time

Deliveries 

  • General construction materials and dumpsters. 

Events for upcoming week

  • Continue exterior tuckpointing West and North exterior.
  • Continue MEP installation throughout.
  • Continue wall layout and framing 3, 4, and 5.
  • Continue wall closing on 2nd floor. 
  • Continue drywall finishing and priming on 1st and 2nd floor.
  • Continue Rooftop HVAC installation.
  • Continue stucco installation at roof exterior.
  • Continue sprinkler system installation.
  • Continue Low voltage installation throughout.
  • Complete jack lift assembly and begin East façade masonry installation.
  • Continue 5th floor Central scaffold installation.
  • Arrow Pest Control to install bait packs in upper floors and ground stations along the South and West along with a liquid treatment along the East ground level.

Recap of Week ending February 25, 2024

  • Continue tuck pointing North and NE brick and limestone.
  • Continue Roof top Stucco work. 
  • Continue low voltage installation.
  • Continue Window restorations.
  • Receive Jack Lift for East elevation brick cladding. Begin assembly.
  • Continue Sprinkler system pipe installation.
  • Electrical shutdown allowed for MDP to be energized.
  • Continue 3rd and interstitial floor duct hanging/ insulation.
  • Continue wall framing on interstitial floors.
  • Continue with 4th floor vaulted ceiling lid installation.
  • Begin installation of 5th floor Central scaffold for ceiling work.
  • Put temp doors on electrical closets and locked the energized panel rooms.
  • Continue MEP throughout.
  • Conducted TUSA site tour 2/23.