Sources of Noise
- Vehicles
- Dumpsters
- Tools/ Equipment
Utility Shutdowns
- None at this time
Deliveries
- General construction materials and dumpsters.
Events for upcoming week
- Continue exterior tuckpointing West and North exterior.
- Continue MEP installation throughout.
- Continue wall layout and framing 3, 4, and 5.
- Continue wall closing on 2nd floor.
- Continue drywall finishing and priming on 1st and 2nd floor.
- Continue Rooftop HVAC installation.
- Continue stucco installation at roof exterior.
- Continue sprinkler system installation.
- Continue Low voltage installation throughout.
- Complete jack lift assembly and begin East façade masonry installation.
- Continue 5th floor Central scaffold installation.
- Arrow Pest Control to install bait packs in upper floors and ground stations along the South and West along with a liquid treatment along the East ground level.
Recap of Week ending February 25, 2024
- Continue tuck pointing North and NE brick and limestone.
- Continue Roof top Stucco work.
- Continue low voltage installation.
- Continue Window restorations.
- Receive Jack Lift for East elevation brick cladding. Begin assembly.
- Continue Sprinkler system pipe installation.
- Electrical shutdown allowed for MDP to be energized.
- Continue 3rd and interstitial floor duct hanging/ insulation.
- Continue wall framing on interstitial floors.
- Continue with 4th floor vaulted ceiling lid installation.
- Begin installation of 5th floor Central scaffold for ceiling work.
- Put temp doors on electrical closets and locked the energized panel rooms.
- Continue MEP throughout.
- Conducted TUSA site tour 2/23.