Reily Natatorium - Week of December 22, 2023

Sources of Noise

  • Utility Vehicles
  • Power Tools
  • Hand Tools 

Utility Shutdowns:

  • None

Deliveries

  • None

Events for upcoming week

  • Continue Phase 2 electrical rough-in
  • Start Phase 2 tile installation
  • Continue Phase 2 framing

Recap of work performed Dec 12-18, 2023

  • Frame the ceiling for support of custom light
  • Complete Phase 2 plumbing rough-in and pressure test system
  • Continue Phase 2 electrical rough-in